03/12/2013

10:15 PM Revision 1e26331d: Merge branch 'master' of 71.178.202.220:/home/dsorber/trac/projects/headquarters/repo
David Sorber
10:15 PM Revision dbe3eff8: Updated the BOM while in "class" last night.
David Sorber
01:54 PM Revision 72edc545: Made the reference designators a bit smaller and made some square pads to designate pin 1's.
dsorber
11:33 AM Revision 8a86f755: Made a few more minor tweaks to the layout. I also moved the LED labels to the silkscreen layer (whoops).
dsorber

03/11/2013

08:33 PM Revision bf56c619: Made a few tweaks to the layout including adding a board name and revision to the silk screen.
dsorber
12:37 PM Revision 8b7ff847: Made a couple of modifications based on Andy's feedback.
dsorber

03/10/2013

08:04 PM Revision dc972317: Finished routing the board! Tomorrow Andy will tell me I did it all wrong...
dsorber

03/09/2013

05:28 PM Revision dd4d4844: Prerouting failsafe commit.
dsorber
04:02 AM Revision 2607c262: Made a few more corrections to the schematic and then started working on the actual PCB layout. The PCB will be approximately 2 inches by 3 inches.
dsorber

03/08/2013

02:50 AM Revision a993b699: Forgot to create PDF of lastest schematic.
dsorber
02:46 AM Revision 1f08bcbd: Finished up schematic and started working on PCB. Then had to go back and fix schematic :( . Finally ran out of steam...
dsorber

03/07/2013

01:59 AM Revision feea6b2c: Finished up the first complete draft of the schematic.
dsorber

03/05/2013

03:05 AM Revision 035b6525: Reworked a couple of the schematic symbols. Also redrew parts of the schematic after getting feedback from Andy.
dsorber

03/04/2013

01:55 AM Revision 1eebfe60: Started working on the schematic. More work needed...